Canada ties scaled Pathways CCS project to new oil export pipeline

Canada, Alberta and five major oil sands producers have signed a non-binding agreement targeting 6mn tonnes a year of carbon capture by 2035. The CCS project is explicitly linked to a proposed 1mn barrel/day pipeline to Canada’s west coast and expanded oil sands production. Binding company commitments, cost allocation, regulatory approvals and a final investment […]

New York imposes first statewide pause on hyperscale data centre development

New York has paused incomplete state environmental permits for data centres of at least 50 MW while it develops new standards. Nearly 12 GW of data centre load requests have entered the state’s interconnection pipeline, although only a fraction is expected to materialise. The most consequential proposal is a “beneficiary pays” regime requiring developers to […]