- All 55 battery units and key electrical equipment for Afon Wysg 1 have been delivered and installed. Ampeak expects commercial operation in the first quarter of 2027.
- The Newport project reused around two-thirds of the former coal station’s export cable, reducing construction time and cost.
- Ampeak has laid foundations for a proposed expansion to 480 MWh and aims to finance it after the first phase enters service.
Ampeak Energy has finished installing the batteries and key electrical equipment for Afon Wysg 1 at the former Uskmouth coal-fired power station in Newport, South Wales.
The company expects the 120 MW / 240 MWh project to be energised later in November, before charge and discharge testing and the planned start of full commercial operation in the first quarter of 2027.
Canadian Solar’s e-STORAGE business supplied the 55 battery units and will handle commissioning. Principal contractor Jones Bros Civil Engineering UK installed the units alongside 36 inverters and the main grid transformer.
Ampeak says the new on-site substation is complete and the high-voltage cabling for the connection has been installed. The delivery programme took 22 days, during which the contractors had to bring equipment to site in the order it was needed.
“Getting the equipment onto site in sequence was the first test,” said Matt Paterson, e-STORAGE’s managing director for Europe, the Middle East and Africa. “Energisation and commissioning is the next, when the batteries and power conversion systems have to perform together as one system on the grid.
“With the foundations for the planned expansion already poured, AW1 is set up to grow without repeating the groundwork. We look forward to working with Ampeak and Jones Bros through those next steps.”
During commissioning, the supplier will test how the battery and power conversion equipment work together on the grid. At its rated output, the project has enough storage for two hours of discharge. EDF has a long-term agreement to optimise the asset once it is operating.
The original project reached financial close in August 2025 with £67.4m in funding, including £45.3m of non-recourse debt from Germany’s NORD/LB. In September 2026, a vehicle owned by directors of Jones Bros acquired a 24.7% stake in the project holding company in a £7.8m transaction that also included the purchase of a shareholder loan. Ampeak retained a 50.6% shareholding.
Shorter route to grid
Uskmouth shows what a former generating site can offer a storage developer beyond available land. Ampeak says reusing around two-thirds of the power station’s export cable saved time and money. It also reused crushed concrete from earlier demolition and brought in bulk aggregates by rail.
The new substation and remaining cabling show how that inheritance can reduce the scope of new works while still requiring a substantial grid construction programme.
The company is applying the same logic to expansion. It has left space between battery units and poured foundations for a proposed doubling of storage capacity to 480 MWh; doing that work now should reduce disruption to the operating battery if the second phase goes ahead.
Afon Wysg 2 is a separate project at Uskmouth, with conditional planning permission for 250 MW and a design that could accommodate up to 1,250 MWh.
For Ampeak, commissioning the first phase will establish how well the repurposed site works as an operating asset. The proposed expansion then has its own investment test: preparing the site in advance can make construction easier, while the case for financing the additional capacity will depend on the revenue available from it and the terms on which the company can raise capital.