- Siemens Energy is the preferred supplier for turbines and offshore substation platforms at SSE’s 1.4 GW Berwick Bank B project.
- SSE estimates the package would support 2,677 UK roles, including 130 new positions identified in Scotland.
- A final contract and SSE’s investment decision are still required, with the latter expected in late 2027.
SSE has selected Siemens Energy as preferred supplier for the turbines and offshore substation platforms at Berwick Bank B, setting out where some of the manufacturing, engineering and servicing work for the 1.4 GW Scottish offshore wind project would take place.
The proposed package spans blade production in Hull, grid and engineering work in northern England and project delivery and servicing in Scotland.
SSE expects the appointment to support 2,222 existing and project-based jobs across Hull, Manchester and Newcastle. The developer identifies a further 455 roles in Scotland, including 80 new SSE jobs in Glasgow and 50 new Siemens Energy positions at Montrose Port.
In Newcastle, the work would include assembly and project delivery for the offshore substations. The appointment remains conditional on a final contract and SSE’s decision to proceed.
The project, in the outer Firth of Forth around 38 km offshore, is one phase of the wider Berwick Bank development, which received Scottish government consent in July 2025. In January, phase B secured a 20-year Contract for Difference for 1,380 MW at £89.49/MWh in 2024 prices.
SSE expects to take its investment decision in late 2027. On that timetable, preparatory offshore works could start in 2028, with turbine and substation installation running from 2030 to 2032.
Where the work could land
“Being selected as preferred supplier for Berwick Bank B brings together some of the very best of Siemens Energy’s UK capabilities,” said Siemens Energy UK and Ireland managing director Darren Davidson.
“While the project remains subject to final approvals and contract award…. Berwick Bank B can play an important role in strengthening the UK’s energy security while supporting industrial capability and supply chains across the country.”
The significance for the supply chain lies in the range of work involved. Blade manufacture gives an existing factory a potential order, engineering and assembly draw on a different workforce and port-based servicing can sustain roles once the construction campaign ends.
SSE had already selected Montrose as its preferred operations and maintenance base in September. In October, it named Aberdeen-based Seaway7 as preferred supplier for work on foundations and array cables. Those earlier announcements and Wednesday’s selection give local suppliers a clearer view of who would procure the work.
They also explain why the latest headcount includes people who would be retained or deployed on the project alongside the new positions identified in Scotland.
An auction award provides a long-term revenue basis for the electricity developers expect to sell, while preferred supplier appointments help them establish the cost and availability of the equipment and services needed to generate power. At Berwick Bank B, SSE is using the period between the two decisions to assemble a delivery plan.
For manufacturers weighing commitments on staff and factory time, the proposed allocation of work identifies where demand would arise. The scale and timing of that demand will firm up when SSE makes the investment decision and awards the contracts.