- Five procurement packages cover fuel and energy systems, testing, plant controls and the integration of equipment across the prototype.
- Each framework has an initial two-year term, with extensions available. Bids are due by 29 January 2027.
- The contracts will support design and testing ahead of the proposed West Burton build. The programme is targeting a grid-connected prototype by 2040.
UK Fusion Energy is seeking industry partners for five engineering packages worth up to £115m for STEP, its proposed prototype fusion power plant at West Burton in Nottinghamshire.
The company announced the procurement on Thursday after publishing the tender notice on Wednesday. It is looking for organisations or consortia to develop and test individual systems and help bring them together in the plant design.
The largest package, worth up to £35m, covers test operations. Its supplier will run test facilities and produce evidence to inform the prototype’s design and safety case. Up to £25m is available for systems engineering and whole-plant integration, while a £15m package covers plant controls.
Two further packages worth up to £20m each cover the breeder blanket, which is intended to recover energy and help produce fuel, and the systems for managing the fuel cycle.
Each framework will have a single supplier, with an initial two-year term and up to two one-year extensions. The value announced by UK Fusion Energy includes those potential extensions, while award decisions are expected in April 2027.
The procurement sits alongside the earlier appointment of ILIOS, a consortium led by Kier and Nuvia, as construction partner under an initial £200m contract.
STEP, short for Spherical Tokamak for Energy Production, is planned for a former coal-fired power station site. The government has allocated £1.3bn to the next phase of the programme as part of more than £2.5bn for fusion over five years.
Its strategy envisages a development consent application by March 2029, with plant construction expected to start from 2030 and operation targeted for 2040.
Testing and integration
UK Fusion Energy says it is the whole-plant integrator. The new integration partner will support that role, helping teams agree the requirements and interfaces that allow equipment designed by different suppliers to operate as one facility.
A design decision in one package can change what another supplier has to deliver, from the capacity of shared services to the way the plant is monitored and controlled. Resolving those dependencies during design can reduce the amount of rework once equipment is ordered or installed.
The test operations package matters for the same reason. Test results can reveal which parts of a design are ready to take forward and which need revision before the programme commits to manufacturing. For engineering and industrial suppliers, that creates work well ahead of the main build.
For government, the value of the procurement will depend on whether it produces evidence that supports later decisions on plant design, consent and construction.